We hope this finds you all well and as the year draws to a close, we would like to say a big thank you, once again, for all your patience and support during the last 12 months of the Sloane Street Transformation works.
As you are aware, all works in the North and South retail areas have now ceased until the New Year. Works in the western residential area will continue until no later than 22/12/2023, when the project from Burberry, right the way down to Tiffany, will have been completed.
Until then, just focussing on works that have already been completed, and those that are currently ongoing, we have the following updates:
Sloane Street Transformation
Sloane Street Lane Closures
Following the last Resident’s Drop-In at Cadogan Hall, it has been confirmed that southbound traffic will be able to continue using Sloane Street throughout the duration of the works. The chicane will remain in place, but move up and down the street, as required.
Trees
New trees are currently being planted along the pavement in the western residential area. Additional trees in the North and South retail areas will be planted early in the New Year.
Cadogan Gate to Pont Street (Footway and Carriageway)
Reach Active’s deep excavation works in the carriageway to the front of Fordie House, have now been completed. FM Conway continue to excavate the temporary tarmac surface to lay the new Yorkstone. Works at this location will continue until the Christmas break.
Pont Street to Hans Street
Paving works continue to move north towards the Danish Embassy.
Sloane Street Junction with Pont Street
Work continuing outside the Cadogan Hotel. Grouting of the new paving outside the entrance to the La Lee Restaurant will be taking place this week. Work will continue into next week at this location, but the barriers will be reduced. Access will remain throughout.
Crossing between 50 Sloane Street and Hermes
The Belisha beacon will be installed within the next week and the crossing will be re-opened.
Join us
At our next residents’ meeting
Thank you to those who attended the Sloane Street Residents Meeting on Tuesday 1 October to receive a project update and discuss the public realm works. Following feedback from residents, we have increased the frequency of these meetings from quarterly to every other month. These dates will be publicised through the newsletter and on our website.
The next meeting will be held on 9th December 2024, 6pm–7pm.
To register for the meeting, please click here.
Should you be unable to join the meeting on Zoom, or if you would prefer a face-to-face meeting, we can arrange this for you. Please email Sloane.Street@fmconway.co.uk in this case.