Sloane Street is home to global luxury retail and a vibrant residential neighbourhood. If Sloane Street blooms, so does London.

 

This website showcases plans to create a stunning green boulevard from Knightsbridge to Sloane Square; with wider pavements, a magnificent planting scheme, elegant street furniture and enhanced lighting.

play button

Working in partnership with the Borough of Kensington & Chelsea

Cadogan and Kensington & Chelsea Council are delivering an exciting multi-million pound public realm programme on Sloane Street. The improvements create an elegant and welcoming environment for pedestrians, without compromising the street’s character or negatively impacting traffic flows. Read more about Our Vision

Consulting the Community

In 2016 & 2017, over 1,100 people took part in a consultation on the Sloane Street proposals, which were approved through the Council’s Key Decision process in April 2019. Over 75% of respondents said they supported the proposals. All responses have been considered, and where possible the feedback has been incorporated into the final design for the street. Read more about The Consultation

Working in partnership with the Borough of Kensington & Chelsea

Cadogan and Kensington & Chelsea Council are delivering an exciting multi-million pound public realm programme on Sloane Street. The improvements create an elegant and welcoming environment for pedestrians, without compromising the street’s character or negatively imacting traffic flows. Read more about Our Vision

Consulting the Community

In 2016 & 2017, over 1,100 people took part in a consultation on the Sloane Street proposals, which were approved through the Council’s Key Decision process in April 2019. Over 75% of respondents said they supported the proposals. All responses have been considered, and where possible the feedback has been incorporated into the final design for the street. Read more about The Consultation

Creating a greener, more elegant neighbourhood for all to enjoy.

Heritage detailing and craftsmanship

Artisan craftsmanship, quality materials and heritage detailing will further enrich the Street’s unique character.

Read more

Sustainability and planting

Climate resiliant planting will create an uplifting environment, add 100 trees to the street and help reduce airborne pollutants on this ultra-low carbon impact scheme

Read more

Improved pedestrian experience

Traffic calming measures, way finders and increased crossing points will help pedestrians navigate the area, without impacting vehicular flow

Read more

Fortnightly Sloane Street Residents’ Update

14 November 2024

The construction of tree pits and planters is at an advanced stage, as public realm works progress south, down the east side of the street. Resurfacing work has already taken place in two of the three sections of the street, with the final, central, section due to be complete by mid December. At the same time, paving and kerb laying continues, progressing well, now that Reach Active has completed its work on utilities upgrades. The removal of barriers in completed sections is already underway, and the northern and southern retail sections have already seen a reduction where footway works are complete. The removal will continue between now and the Christmas light switch-on as further work areas are finished. 

The latest figures on work completed to date are also included below.

Christmas Lights

MK Illumination has commenced the installation of the new Sloane Street Christmas Lighting scheme, on behalf of Cadogan. Please bear with us whilst these works are carried out in time for the Christmas Lights Switch-On event on Saturday 16th November 2024. If you do have any concerns, please don’t hesitate to contact mark.poole@cadogan.co.uk.

Directional closure of Sloane Street

Traffic continues to travel in a southbound direction down the west side of the street whilst public realm works take place to the eastern footway. A copy of the traffic management and associated diversion routes can be found here.

Road closures

Cadogan Place North remains closed whilst a new CCTV post is installed and connected. The road is expected to reopen in early December, once resurfacing work is complete.

The junction of Cadogan Place south is now closed until early December for the installation of the drinking water fountain. A mini compound will be established to allow FM Conway to work on the raised table across the road.

Temporary traffic lights at Pont Street

A temporary three-way traffic light system has been in operation at the junction with Pont Street since late July, to enable the construction of the new granite crossings at the junction with Sloane Street.

Transport for London has been upgrading the signalling infrastructure in preparation for the installation of the new traffic lights for the final completed scheme. The last column for the permanent lighting is anticipated to be installed this week. TfL will then complete the connections, with a date for this yet to be confirmed.

Bus services

The bus stop outside of Holy Trinity Church has been reopened, following the completion of recent resurfacing works in this area. Bus stop H has also reopened towards Battersea, Chelsea & Knightsbridge following the completion of gas works.

Stop KL, adjacent to Pont Street, is currently suspended, and will reopen following the completion of resurfacing works in this area in mid December.

Latest works updates

Cadogan Place north junction

The CCTV installation is still outstanding, and is anticipated to be completed during the early weeks of 2025.

Holy Trinity Church to Sloane Square

FM Conway has completed the remaining public realm works here, with grouting, cleaning and sealing to taking place over this coming week. The resurfacing and road markings are now complete. A number of traffic management barriers will remain in situ for safety reasons until Sloane Street reverts to two way traffic.

Sloane Terrace

FM Conway will be completing the installation of the wayfinding signage here.

Completion of loading bays

Loading bays to the front of Hermes and Oliver People will be grouted cleaned and sealed in preparation for reopening, prior to the Christmas Lights switch-on.

Snagging

Snagging works will commence at several locations along Sloane Street. These will be completed before retail units open for trading.

Cycle Stands

Cycle stands will be installed in front of Dior.

Resurfacing works

Much of the resurfacing work is now complete, with only the central section of Sloane Street between Cadogan Place North and Cadogan Place South remaining to be resurfaced.

  • Central Section (Phase 1 – Cadogan Place North to Pont Street) – 04/12/2024 (4 Nights).
  • Central Section (Phase 2 – Pont Street to Cadogan Place South) – 10/12/2024 (4 Nights).

Please note, the dates and times of this work are only indicative and may take longer than expected if the site team encounters any unforeseen difficulties, such as engineering challenges or bad weather.

Works completed up to 31 October 2024

Of 8500m2 of paving, 88% (approximately 7500m2) has been laid.

Of 2800m of kerbs, 88% (approximately 2450m) has been laid.

Of 1300m2 of setts, 81% (approximately 1050m2) has been laid.

Of 46 planters, 87% (40) have been installed.

Of 47 plant pots, 81% (38) have been installed.

Of 54 tree pits, 63% (34) have been constructed.

Figures on completed works will be updated in December

Ongoing works

Brompton Road to Harriet Street

Paving works are now complete in this section, with snagging work underway whilst the installation of street furniture continues.  

Harriet Street to Cadogan Place North

Work to the front of Gina and Roger Vivier is almost complete, with the installation of a combined lamp column and Belisha beacon taking place from 14th November. Meanwhile, bespoke tiling on the forecourts at Chanel, Pucci and St Laurent continues.

Cadogan Place north to Pont Street

Work continues on the eastern footway, including paving, grouting and installation of the relocated bus shelter.

Pont Street to Cadogan Place South

Paving and kerbing works at the southeastern corner of Pont Street are still ongoing. Meanwhile, further south, work continues on construction of the granite planters, tree pits and re-paving.

Cadogan Place South to Sloane Square

Most of the paving in this section has been completed, with grouting and sealing work continuing in isolated sections.

Please note, the dates and times of this work are only indicative and may take longer than expected if the site team encounters any unforeseen difficulties, such as engineering challenges or bad weather.

Join us

At our next residents’ meeting

Thank you to those who attended the Sloane Street Residents Meeting on Tuesday 1 October to receive a project update and discuss the public realm works. Following feedback from residents, we have increased the frequency of these meetings from quarterly to every other month. These dates will be publicised through the newsletter and on our website.

The next meeting will be held on 9th December 2024, 6pm–7pm.

To register for the meeting, please click here.

Should you be unable to join the meeting on Zoom, or if you would prefer a face-to-face meeting, we can arrange this for you. Please email Sloane.Street@fmconway.co.uk in this case.

Skip to content