RBKC and their contractor FM Conway currently have nine active worksites on Sloane Street.

Works completed so far…

  • Out of 8500m2 of paving, approximately 6700m2 has already been laid.
  • Out of 2800m of kerbs, approximately 2300m has already been laid.
  • Out of 1300m2 of setts (smaller blocks) approximately 900m2 has already been laid.
  • Out of 46 planters, 40 have already been installed.
  • Out of 47 plant pots 34 have already been installed.
  • Out of 54 tree pits 32 have been constructed.
Sloane Street Transformation

North Sloane Street

Following the carriageway resurfacing works in the northern section of Sloane Street, the green barrier removal is already underway, and there is already a reduction where footway works are complete.  The barrier removal will continue between now and the Christmas light switch-on as further work areas are finished.  

RBKC is installing the thin paver tiles in the northern section and paving works are progressing well outside the Jumeirah Carlton Tower service entrance. The granite blocks are now being installed outside Hermès, as well as nearing completion at the Pont Street junction. Also here, TfL are installing the new intelligent adaptive traffic signals that enable optimisation of green time for all street users, including pedestrians, bicycles, buses and cars in a world first. This new system will deliver improved journey times, traffic flows and responses to incidents.

Cadogan Place Gardens

RBKC works are ongoing alongside Cadogan Gardens. There are just six more planters remaining to be installed.

South Sloane Street

The final granite blocks are now being installed outside Diptyque, with works ongoing to complete the granite raised table across Sloane Terrace, outside Jo Malone London.

The carriageway resurfacing at the southern end of Sloane Street was able to be completed earlier than expected and the removal of the green barriers will continue between now and the Christmas light switch-on, as further work areas are finished.

FM Conway 2024 Timetable

The timetable for the public realm works on the east side of Sloane Street can be found at www.sloanestreetfuture.co.uk/programme

Full plans of the completed scheme can be found at www.sloanestreetfuture.co.uk/our-vision.

Security and Operations

Please join the Safer West Central – Business Resilience Forum on Wednesday 20th November, between 3pm – 4pm. Connect with store and security managers, Metropolitan Police, and RBKC and Westminster City Council representatives to discuss crime trends, intelligence on prolific offenders, and operational updates. The forum is online via Microsoft Teams, accessible through desktop, browser, or smartphone app. Sign up here.