July 2024

By way of a recent update, work on the kerbstones and Yorkstone paving continues along the east side of the street. Planters are being installed on the footways and the team continues to construct raised tables. RBKC and contractor FM Conway currently have five active worksites on Sloane Street, meanwhile Reach Active have now been demobilised from Sloane Street.

Sloane Street Transformation

North Sloane Street

From Harriet Street to Cadogan Place the public realm works are ongoing and TfL have finally moved the bus shelter outside Louis Vuitton to the correct, new location. The Yorkstone paving is now being completed in this area.

Cadogan Place Gardens

The installation of the Public Realm works along the edge of the gardens is ongoing.

South Sloane Street

The installation of the Public Realm works is ongoing from Sloane Terrace to Ellis Street. Paving has been laid to the south end of this worksite and the planters have been installed. Outside Holy Trinity Church, the planter is being installed and preparations are underway for the new, Yorkstone paving.

FM Conway 2024 Timetable

The timetable for the public realm works on the east side of Sloane Street can be found at www.sloanestreetfuture.co.uk/programme

Full plans of the completed scheme can be found at www.sloanestreetfuture.co.uk/our-vision.

Security and Operations

Please join the Safer West Central – Business Resilience Forum on Wednesday 21st August, between 3pm-4pm. Connect with store and security managers, Metropolitan Police, and RBKC and Westminster council representatives to discuss crime trends, intelligence on prolific offenders, and operational updates. The forum is online via Microsoft Teams, accessible through desktop, browser, or smartphone app. Sign up here.

Skip to content