RBKC and their contractor FM Conway currently have 5 active worksites on Sloane Street:

  • Outside Louis Vuitton to outside Ermanno Scervino
  • Opposite the Millenium Hotel
  • Outside Cadogan Place Gardens
  • Cadogan Place to Ellis Street
  • Outside Holy Trinity Church

Reach Active have two worksites:

  • Thames Water is on site carrying out the commissioning of the water main
  • Programmed works ongoing
Sloane Street Transformation

North Sloane Street

RBKC works are ongoing in the worksite from outside Louis Vuitton to outside Ermanno Scervino, excavations have taken place to the south of this worksite in preparation for the installation of the Public Realm Scheme. RBKC continue to install the Public Realm Scheme to the north of this worksite. In addition, works have commenced opposite the Millennium Hotel, excavations are ongoing in preparation for the installation of the Public Realm Scheme.

New granite kerbstones and Yorkstone pavers have been laid outside Harvey Nichols

Reach Active’s programmed utility lowering works are ongoing outside Bulgari to outside Hermes. Reach Active have also now commenced backfilling the northern end of this worksite.

Cadogan Place Gardens

RBKC works are ongoing outside Cadogan Place Gardens, the more southern planters have been installed along with soil and planting. The slabs have been installed around these. The planters further north in this worksite have been set out in preparation for the installation of the planter base foundations.

The footpath has been excavated

South Sloane Street

RBKC works to the footway outside Holy Trinity Church are largely complete, the majority of the footway has been reopened. 

RBKC works are ongoing between Cadogan Place and Ellis Street, the worksite has been excavated and the planter bases have been marked out for the foundations to be installed.

New granite kerbstones and Yorkstone pavers have been laid outside Harvey Nichols

Thames Water

Thames Water commissioning, managed by Reach Active, is ongoing along Sloane Street, linking side streets to the new pipeline.

New granite kerbstones and Yorkstone pavers have been laid outside Harvey Nichols

FM Conway 2024 Timetable

The timetable for the public realm works on the east side of Sloane Street can be found at www.sloanestreetfuture.co.uk/programme

Full plans of the completed scheme can be found at www.sloanestreetfuture.co.uk/our-vision).

New granite kerbstones and Yorkstone pavers have been laid outside Harvey Nichols
Sustainability

You will all no doubt be familiar with the sight of the e-cargo bike whizzing quietly up and down Sloane Street to perform its waste collection duties (see below). The waste is then taken to a waste consolidation point tucked just behind Sloane Street, with the e-cargo bike currently supporting bag deliveries and collections for 80+ Cadogan occupiers on Sloane Street, the King’s Road and surrounding areas. This is quieter, more convenient, and also has the environmentally positive benefits of both improving air quality and reducing emissions (by 36% when compared with collection by an average truck).

We have also seen a moderate but nevertheless encouraging 2% rise in commercial recycling on Sloane Street in the last year – please email sustainability@cadogan.co.uk if you would like to achieve more in this regard.

Security and Operations

Please join the Safer West Central – Business Resilience Forum on Wednesday 17th April between 3pm-4pm. Connect with store and security managers, Metropolitan Police, and RBKC and Westminster council representatives to discuss crime trends, intelligence on prolific offenders, and operational updates. The forum is online via Microsoft Teams, accessible through desktop, browser, or smartphone app. Sign up here.